Frequently asked questions
When does it make sense to appoint a DAB during construction?
A standing board knows the project and its documents from the outset, so it decides faster and can help prevent disagreements. It does, however, incur ongoing costs even if no dispute arises. An ad hoc board is constituted only once a dispute arises and is cheaper, but needs time to become familiar with the project. The choice depends on the size and risk profile of the project.
Is a DAB decision binding?
Yes. The parties must give effect to a DAB decision promptly. A party that disagrees may give a Notice of Dissatisfaction within the contractual time limit; the decision then remains binding unless and until it is revised by an amicable settlement or an arbitral award. If no Notice of Dissatisfaction is given in time, the decision becomes final.
How are the fees of an arbitrator and a DAB member determined?
For a DAB or DAAB, fees are agreed in the tripartite agreement, usually as a monthly retainer and a daily rate, and are shared equally by the parties. In institutional arbitration they follow the institution's scale of fees; in ad hoc proceedings, the arbitrator's contract.